Progress invoicing in QuickBooks Online lets you split one accepted estimate into as many invoices as the job needs, so you bill as work is completed instead of asking for full payment up front or at the end. You turn the feature on in your account settings, build an estimate, then convert it into invoices by percentage or by line item. QuickBooks keeps every invoice linked to the estimate and tracks what has been billed and what is left.
This guide walks through the setup, shows worked examples with real arithmetic, explains how to track the remaining balance, and covers the bookkeeping habits that keep staged billing clean.
TL;DR
- Progress invoicing splits a single estimate into multiple invoices, billed by percentage or by selected line items as work is completed.
- Turn it on under Settings > Account and settings > Sales, then create an estimate for the customer.
- Use the Estimates & Progress Invoicing Summary by Customer report to see what you have invoiced and what is left.
- It tracks what you billed, not what the customer paid, so pair it with payment records or statements.
- Choose it when payment is tied to stages. Choose partial payments when one invoice already exists.
Table of Contents
- What progress invoicing does in QuickBooks Online
- How to turn on progress invoicing
- Create progress invoices from an estimate
- Track what you have billed and what remains
- Editing and unlinking a progress invoice
- Progress invoices or partial payments?
- Billing habits that keep stage invoices clean
- Our perspective on staged billing
- Get your QuickBooks billing set up properly
- FAQ
- Sources
What progress invoicing does in QuickBooks Online
Staged billing is common wherever a job runs for weeks or months: construction and remodeling, agencies, consultants, equipment installs, custom manufacturing. Instead of one big invoice at the end, you send several smaller ones tied to deposits, milestones or completion percentages.
In QuickBooks Online, progress invoicing lets you split an estimate into as many invoices as you need. You invoice a percentage of the estimate or selected line items as work is completed. QuickBooks keeps the invoices connected to the estimate and tracks the amounts already invoiced against the remaining balance, and it will not let you add more than what remains.
That linkage is the real value. You are not retyping numbers into a spreadsheet and hoping they add up to the contract. The estimate is the single source of truth, and every invoice draws it down.
Investopedia describes the same logic: progress billings suit large, long-term projects because the client does not pay everything up front, and the contractor receives regular payments that cover ongoing costs such as materials. Payments follow a verified percentage of completion, and the final balance is usually paid once the project is finished and the client is satisfied.

How to turn on progress invoicing
Before you start, you need two things: the feature enabled and an estimate for the customer. Intuit's U.S. guide lists exactly those two prerequisites.
- Sign in to QuickBooks Online as an admin.
- Go to Settings, then Account and settings, then the Sales tab.
- Find the Progress Invoicing section and select the pencil icon to edit it.
- Turn on "Create multiple partial invoices from a single estimate."
- Select Done.
The setting is company-wide, so it applies to every estimate from then on. If you also use a desktop version of QuickBooks, the steps differ, and Intuit publishes a separate guide for that product.
A tip from our bookkeeping desk: before you switch this on for a real customer, make sure your products and services list is tidy. Progress invoicing bills line items, and vague or duplicated items make for confusing invoices. If your item list or chart of accounts is a mess, our guide to fixing a QuickBooks chart of accounts is a good place to start, and our QuickBooks setup walkthrough covers the foundation.
Create progress invoices from an estimate
Once the customer accepts the estimate, there are two ways to begin. Per Intuit, you can open the accepted estimate and select Convert to invoice, or start a new invoice and add the estimate from Suggested transactions.
QuickBooks then asks how much of the estimate to bill. You can choose:
- The entire estimate, which works like a normal invoice.
- A percentage of the total, useful for deposits and milestone payments.
- Selected line items, useful when parts of the job are delivered separately.
Copy your selection to the invoice, review it, then save or send. Repeat for each stage until the estimate is fully billed.
Worked example: billing by percentage
Say a $40,000 kitchen remodel is accepted as a single estimate with a 30/40/30 billing plan. This is an illustration, not a real client.
| Invoice | Trigger | Percent | Amount | Remaining on estimate |
|---|---|---|---|---|
| 1 | Signed contract (deposit) | 30% | $12,000 | $28,000 |
| 2 | Cabinets and plumbing rough-in done | 40% | $16,000 | $12,000 |
| 3 | Final walkthrough | 30% | $12,000 | $0 |
Each row is its own invoice with its own due date. Add up the three and you get $40,000, the full estimate. Because every invoice is linked to the estimate, the remaining column is something QuickBooks tracks for you.
Worked example: billing by line item
Now take a $40,000 estimate with three lines: design at $5,000, build at $30,000, and installation at $5,000. Design is finished and half the build is done.
- Invoice design at 100%: $5,000.
- Invoice build at 50%: $15,000.
- Invoiced to date: $20,000.
- Left to invoice: $20,000 ($15,000 of build and $5,000 of installation).
Line-item billing is the better fit when the pieces of a job really are separate deliverables, because the invoice description can match what the client received.
Bigger jobs: project phases
If your estimates have dozens of lines, billing line by line gets tedious. Intuit's project-phase guide says QuickBooks Online Advanced and Intuit Enterprise Suite can group estimates and invoices into phases such as Site Prep or Electrical. You can then bill a percentage of a whole phase, or a dollar amount for particular line items, instead of editing every child line. That is a cleaner way to bill when a phase is one deliverable in the client's eyes.
Track what you have billed and what remains
The most common progress billing complaint is not a software problem. It is a communication problem. A client who cannot see the original contract amount, what was billed before, what this invoice charges and what is left will stall approvals while they rebuild the math from old emails. Show the roll-forward on every invoice.
Inside QuickBooks, there are three ways to see it:
- Linked transactions. Open any invoice and select Linked transactions to jump to the source estimate and the related invoices.
- The Estimates & Progress Invoicing Summary by Customer report. It shows estimate totals, the amounts invoiced, and the amounts left to invoice.
- Invoice columns. According to Intuit's phase guide, invoice customization can show Total, Invoiced and Remaining columns, so the customer sees the agreed amount, the previously billed amount and what is still to bill.
For a rule of thumb on what a progress bill should contain, Investopedia lists the total contract amount, any approved changes, the adjusted amount owed, the total billed so far, the current completion percentage and the remaining balance at completion. If your invoice template cannot show those, adjust it before your next staged job.
Billed is not the same as paid
This trips up many owners. Progress invoicing records what you have invoiced against an estimate. It does not by itself tell you whether earlier invoices were paid. If a client asks "what do I still owe," use a customer statement or your accounts receivable aging report, not the estimate summary. Keep both views in your routine: one for billing progress, one for collections.

Payments also need to land in the right place. If deposits pile up in the wrong account, your receivables will not match reality, and our guide to QuickBooks Undeposited Funds explains how to keep that clean.
Editing and unlinking a progress invoice
Mistakes happen: a wrong percentage, a line billed too early, an invoice that should stand alone. To unlink an invoice from its estimate, open the invoice, select Linked transactions and choose Remove beside the estimate. Once unlinked, that invoice no longer draws down the estimate, so check the summary report afterward to confirm the remaining balance is what you expect.
For edits to an invoice that is still linked, change the amounts on the invoice itself and re-check the remaining balance on the estimate. When a change order alters the scope, update the estimate or add a separate one so the totals still tie to the signed contract, and keep a written record of the approval.
Progress invoices or partial payments?
These two tools sound alike and solve different problems. The practical test is when the stages are defined.
| Situation | Better tool |
|---|---|
| You know the stages before work starts and bill each one separately | Progress invoicing from an estimate |
| One invoice already exists and the client wants to pay it in installments | Partial payments or a payment plan |
| Each stage needs its own due date and description | Progress invoicing |
| Payment is tied to delivery milestones on a long project | Progress invoicing |
With progress invoicing, you get separate invoices, each with its own due date and balance. With partial payments, one invoice stays open with a running balance. If your contract says "30% at signing, 40% at rough-in, 30% at completion," progress invoicing mirrors it. If you already sent a $9,000 invoice and the client asks to pay $3,000 a month, that is a payment arrangement, not staged billing.
Whichever you choose, spell the stages out in the estimate or contract, set each due date to match the delivery of that stage, and write each invoice description in terms of what was delivered. That makes approval easy for the client's accounts payable team.
Billing habits that keep stage invoices clean
- Write the billing schedule into the contract. The estimate should match it exactly, so no one argues over percentages later.
- Bill when the milestone is met, not when you remember. Late invoices are the leading cause of cash flow gaps on long jobs.
- Use descriptive line items. "Phase 2: rough-in complete" beats "Progress payment 2."
- Handle change orders deliberately. Document them, then reflect them in the estimate so the adjusted contract total is visible.
- Reconcile monthly. Compare the progress summary report to your receivables and your work-in-progress records.
- Track costs by job. Staged billing tells you what you charged. Job costing tells you whether the job made money. See our five job costing setup steps for QuickBooks and project accounting basics.
If your clients are service buyers who sometimes want to add a gratuity or thank-you at the end of a staged job, it can help to add a tip option to your service invoice so the final payment stays simple and traceable.
Once billing is in good shape, look at what the numbers say. Staged invoices make revenue timing visible, and that feeds cash flow forecasts and margin analysis. A break even analysis using your QuickBooks data is a natural next step for a business that bills by milestone.
Our perspective on staged billing
Most of the progress invoicing problems we see are not feature problems. They are books problems. The estimate was built with loose items, the chart of accounts has overlapping income accounts, deposits were recorded as regular income, and nobody can say with confidence how much of a contract remains unbilled.
At AmCFO, we treat staged billing as part of a bigger picture: clean setup first, then a billing schedule that matches the contract, then reporting that connects what was billed to what was collected and what the job actually cost. The feature takes minutes to turn on. The discipline around it is what protects your cash flow.
Every accounting engagement we run comes with experienced fractional CFO oversight, so the person reviewing your books is also looking at what the numbers mean for your decisions: when to bill, how much work in progress you are carrying, and whether a job is earning the margin you quoted. Because our approach is modular, you can choose the pieces you need, from cleanup and QuickBooks support to forecasting, without the cost of a full-time executive.
If your progress invoices do not tie out to your estimates and your receivables, fix the foundation before you add more jobs on top of it.
Angelica
Get your QuickBooks billing set up properly
If you would rather have staged billing running correctly than spend weekends sorting it out, we can help. Our team handles QuickBooks setup, support and cleanup, so your estimates, items and invoices work together from the first job. We serve both for-profit and non-profit organizations, and we tailor the work to the way your business bills.

For ongoing bookkeeping and financial management, see our accounting and bookkeeping services. If you want help reading what your billing data says about margins and cash, our fractional CFO services bring that oversight without a full-time hire. If your books already need a reset, start with our 12-step QuickBooks cleanup guide.
FAQ
How do I turn on progress invoicing in QuickBooks Online?
Go to Settings, then Account and settings, then Sales. Edit the Progress Invoicing section, turn on "Create multiple partial invoices from a single estimate," and select Done. You also need an estimate for the customer before you can create progress invoices.
Can I invoice only some line items from an estimate?
Yes. When you convert the estimate, you can choose the whole estimate, a percentage, or selected line items. QuickBooks tracks what has been invoiced on each, and it will not let you bill more than the remaining balance.
How do I see what is left to bill on an estimate?
Open an invoice and select Linked transactions to reach the estimate and its related invoices. For a broader view, run the Estimates & Progress Invoicing Summary by Customer report, which shows estimate totals, invoiced amounts and amounts left to invoice.
Does progress invoicing show whether the customer has paid?
Not on its own. It tracks amounts invoiced against the estimate. To see what a customer has actually paid, use payment records, a customer statement or your receivables aging report alongside the progress summary.
What is a good example of a progress invoice?
A $40,000 job billed 30/40/30 produces invoices of $12,000, $16,000 and $12,000. Each invoice should show the contract amount, the amount billed before it, the current charge and the remaining balance, so the client never has to rebuild the math.
Sources
- Set up and send progress invoices, QuickBooks Online support
- Group line items by project phases on estimates and invoices, QuickBooks support
- Understanding Progress Billings: Key Concepts and Benefits, Investopedia